H.R. 4346 — CHIPS and Science Act of 2022
Official title: An Act making appropriations for the Legislative Branch for the fiscal year ending September 30, 2022, and for other purposes (enacted as the CHIPS and Science Act of 2022; Public Law 117-167).
117th Congress · Enrolled (enacted, Public Law) · reported Aug. 9, 2022 · read the full bill text →
Where the money goes
$54.2B across 27 tracked itemsThe largest verified line-items. This pie breaks down the biggest spending items in the bill — appropriations and mandatory (direct) spending — by category. Every dollar is quoted from the text; click any slice to read them. It is not necessarily every dollar in the bill (the smallest items may not be listed), and figures that aren’t spending — authorizations, guarantee ceilings, pay-fors, and carve-outs already counted — are deliberately left out and disclosed below.
Authorizations (a ceiling on future spending) — $54.2B
“There are authorized to be appropriated $X” sets a CAP on what a future appropriations bill may provide — it is permission, not money. Much of a landmark law’s headline figure is this. It is disclosed here, never summed into the pie, because the cash only exists if a later bill actually appropriates it.
- National Science Foundation total authorization of appropriations, FY2027 (final year of the 5-year ramp)$18.9B
- National Science Foundation total authorization of appropriations, FY2023 (ramps to $18.9B by FY2027)$11.9B
- Department of Energy Office of Science total authorization of appropriations, FY2023 (~$50B over FY2023-2027)$8.9B
- Regional Technology and Innovation Hubs program authorization, FY2025-2027 (EDA regional tech hubs)$7.0B
- DOE Basic Energy Sciences program authorization, FY2023 (within the DOE Office of Science total)$2.7B
- National Institute of Standards and Technology total authorization of appropriations, FY2023$1.6B
- Authorization for NSF's new Directorate for Technology, Innovation & Partnerships, FY2023 (within NSF R&RA total)$1.5B
- Distressed Area Recompete Pilot Program authorization (EDA grants to persistently distressed communities)$1.0B
- Construction of the Electron-Ion Collider, FY2027 (DOE nuclear physics user facility)$301.0M
- Construction of the Spallation Neutron Source Second Target Station, FY2025 (DOE Office of Science user facility)$279.0M
- Construction of the Long-Baseline Neutrino Facility (LBNF) for the international Deep Underground Neutrino Experiment (DUNE), FY2023 (~$1.35B FY2023-2027)$180.0M
Loan-guarantee ceilings — $75.0B
Caps on NEW loan or mortgage-backed-security guarantee commitments. No cash is spent — the government only backstops private lending — so these are excluded from the pie entirely.
- Ceiling on gross obligations for principal of direct loans/guarantees financed by the CHIPS Fund (NO cash outlay)$75.0B
Every dollar, cited
27 spending line-itemscommerce & housing credit$45.0B · 83%
- CHIPS for America Fund, FY2022 portion for semiconductor manufacturing incentives (grants/financial assistance, NDAA sec. 9902)$19,000,000,000
“…until expended, of which $19,000,000,000 shall be for…”
Division A (CHIPS Act of 2022), Sec. 102(a)(2) — CHIPS for America Fund, FY2022 - CHIPS for America Fund, FY2023 appropriation (semiconductor manufacturing incentives + R&D)$7,000,000,000
“…(ii)for fiscal year 2023, $7,000,000,000 to remain available…”
Division A, Sec. 102(a)(2) — CHIPS for America Fund, FY2023 - CHIPS for America Fund, FY2026 appropriation (semiconductor manufacturing incentives + R&D)$6,600,000,000
“…and (v)for fiscal year 2026, $6,600,000,000, to remain…”
Division A, Sec. 102(a)(2) — CHIPS for America Fund, FY2026 - CHIPS for America Fund, FY2024 appropriation (semiconductor manufacturing incentives + R&D)$6,300,000,000
“…116–283; (iii)for fiscal year 2024, $6,300,000,000, to remain…”
Division A, Sec. 102(a)(2) — CHIPS for America Fund, FY2024 - CHIPS for America Fund, FY2025 appropriation (semiconductor manufacturing incentives + R&D)$6,100,000,000
“…(iv)for fiscal year 2025, $6,100,000,000, to remain…”
Division A, Sec. 102(a)(2) — CHIPS for America Fund, FY2025
science$5.0B · 9%
- CHIPS for America Fund, FY2022 portion for the National Advanced Packaging Manufacturing Program (NDAA sec. 9906(d))$2,500,000,000
“…Public Law 116–283, $2,500,000,000 shall be for…”
Division A, Sec. 102(a)(2) — CHIPS for America Fund, FY2022 (sec. 9906(d)) - CHIPS for America Fund, FY2022 portion for the National Semiconductor Technology Center (NDAA sec. 9906(c))$2,000,000,000
“…Public Law 116–283, $2,000,000,000 shall be for…”
Division A, Sec. 102(a)(2) — CHIPS for America Fund, FY2022 (sec. 9906(c)) - CHIPS for America Fund, FY2022 portion for microelectronics metrology R&D and Manufacturing USA (NDAA sec. 9906(e)-(f))$500,000,000
“…Law 116–283, and $500,000,000 shall be for…”
Division A, Sec. 102(a)(2) — CHIPS for America Fund, FY2022 (sec. 9906(e)&(f))
defense$2.0B · 4%
- CHIPS for America Defense Fund, FY2023 (DoD microelectronics; $400M/yr FY2023-2027, $2,000,000,000 total)$400,000,000→ Department of Defense
“…otherwise appropriated— (A)for fiscal year 2023, $400,000,000, to remain…”
Division A, Sec. 102(b)(2) — CHIPS for America Defense Fund, FY2023 - CHIPS for America Defense Fund, FY2024 (DoD microelectronics; $400M/yr FY2023-2027, $2,000,000,000 total)$400,000,000→ Department of Defense
“…(B)for fiscal year 2024, $400,000,000, to remain…”
Division A, Sec. 102(b)(2) — CHIPS for America Defense Fund, FY2024 - CHIPS for America Defense Fund, FY2025 (DoD microelectronics; $400M/yr FY2023-2027, $2,000,000,000 total)$400,000,000→ Department of Defense
“…30, 2024; (C)for fiscal year 2025, $400,000,000, to remain…”
Division A, Sec. 102(b)(2) — CHIPS for America Defense Fund, FY2025 - CHIPS for America Defense Fund, FY2026 (DoD microelectronics; $400M/yr FY2023-2027, $2,000,000,000 total)$400,000,000→ Department of Defense
“…(D)for fiscal year 2026, $400,000,000, to remain…”
Division A, Sec. 102(b)(2) — CHIPS for America Defense Fund, FY2026 - CHIPS for America Defense Fund, FY2027 (DoD microelectronics; $400M/yr FY2023-2027, $2,000,000,000 total)$400,000,000→ Department of Defense
“…2026; and (E)for fiscal year 2027, $400,000,000, to remain…”
Division A, Sec. 102(b)(2) — CHIPS for America Defense Fund, FY2027
broadband$1.5B · 3%
- Public Wireless Supply Chain Innovation Fund, FY2023 (Open RAN / wireless supply chain innovation)$1,350,000,000→ NTIA (Public Wireless Supply Chain Innovation Fund)
“…2031; and (2)$1,350,000,000 for fiscal year 2023, to remain…”
Division A, Sec. 106 — Appropriations for wireless supply chain innovation - Public Wireless Supply Chain Innovation Fund, FY2022 (Open RAN / wireless supply chain; $1.5B total with FY2023)$150,000,000→ NTIA (Public Wireless Supply Chain Innovation Fund)
“…(1)$150,000,000 for fiscal year 2022, to remain…”
Division A, Sec. 106 — Appropriations for wireless supply chain innovation
other$519.4M · 1%
- CHIPS International Technology Security & Innovation Fund, FY2023 ($100M/yr; $500,000,000 total)$100,000,000→ Dept. of State / USAID / EXIM / DFC
“…(i)for fiscal year 2023, $100,000,000, to remain…”
Division A, Sec. 102(c)(2) — CHIPS Int'l Tech Security & Innovation Fund, FY2023 - CHIPS International Technology Security & Innovation Fund, FY2024 ($100M/yr; $500,000,000 total)$100,000,000→ Dept. of State / USAID / EXIM / DFC
“…30, 2027; (ii)for fiscal year 2024, $100,000,000, to remain…”
Division A, Sec. 102(c)(2) — CHIPS Int'l Tech Security & Innovation Fund, FY2024 - CHIPS International Technology Security & Innovation Fund, FY2025 ($100M/yr; $500,000,000 total)$100,000,000→ Dept. of State / USAID / EXIM / DFC
“…(iii)for fiscal year 2025, $100,000,000, to remain…”
Division A, Sec. 102(c)(2) — CHIPS Int'l Tech Security & Innovation Fund, FY2025 - CHIPS International Technology Security & Innovation Fund, FY2026 ($100M/yr; $500,000,000 total)$100,000,000→ Dept. of State / USAID / EXIM / DFC
“…30, 2029; (iv)for fiscal year 2026, $100,000,000, to remain…”
Division A, Sec. 102(c)(2) — CHIPS Int'l Tech Security & Innovation Fund, FY2026 - CHIPS International Technology Security & Innovation Fund, FY2027 ($100M/yr; $500,000,000 total)$100,000,000→ Dept. of State / USAID / EXIM / DFC
“…(v)for fiscal year 2027, $100,000,000, to remain…”
Division A, Sec. 102(c)(2) — CHIPS Int'l Tech Security & Innovation Fund, FY2027 - Supplemental appropriation for U.S. Marshals Service to address threats to the Supreme Court$10,300,000→ U.S. Marshals Service (Dept. of Justice)
“…additional amount for Salaries and Expenses, $10,300,000, to remain…”
Division C, Title I — Dept. of Justice, U.S. Marshals Service, Salaries and Expenses - Supplemental appropriation for the Supreme Court to address threats to the Supreme Court$9,100,000→ Supreme Court of the United States
“…additional amount for Salaries and Expenses, $9,100,000, to remain…”
Division C, Title II — The Judiciary, Supreme Court of the United States, Salaries and Expenses
education$200.0M · 0%
- CHIPS for America Workforce and Education Fund, FY2025 (NSF microelectronics workforce; $200,000,000 total)$50,000,000→ National Science Foundation
“…(C)for fiscal year 2025, $50,000,000, to remain…”
Division A, Sec. 102(d)(2) — CHIPS Workforce and Education Fund, FY2025 - CHIPS for America Workforce and Education Fund, FY2026 (NSF microelectronics workforce; $200,000,000 total)$50,000,000→ National Science Foundation
“…until expended; (D)for fiscal year 2026, $50,000,000, to remain…”
Division A, Sec. 102(d)(2) — CHIPS Workforce and Education Fund, FY2026 - CHIPS for America Workforce and Education Fund, FY2027 (NSF microelectronics workforce; $200,000,000 total)$50,000,000→ National Science Foundation
“…(E)for fiscal year 2027, $50,000,000, to remain…”
Division A, Sec. 102(d)(2) — CHIPS Workforce and Education Fund, FY2027 - CHIPS for America Workforce and Education Fund, FY2023 (NSF microelectronics workforce; $200,000,000 total)$25,000,000→ National Science Foundation
“…(A)for fiscal year 2023, $25,000,000, to remain…”
Division A, Sec. 102(d)(2) — CHIPS Workforce and Education Fund, FY2023 - CHIPS for America Workforce and Education Fund, FY2024 (NSF microelectronics workforce; $200,000,000 total)$25,000,000→ National Science Foundation
“…until expended; (B)for fiscal year 2024, $25,000,000, to remain…”
Division A, Sec. 102(d)(2) — CHIPS Workforce and Education Fund, FY2024
How this was built
Fetched the enrolled bill XML from GovInfo (response bytes decoded as UTF-8); produced faithful text via ElementTree itertext join; located each dollar figure by disambiguated substring search and extracted a newline-free, <=15-word verbatim quote; every amount and quote re-verified as an exact substring of that text. 39 of 39 sampled figures were re-located as exact strings in the source text. Source: GovInfo enrolled bill text. Full bill text.
SOURCING: All line items are exact-verified substrings of the ENROLLED (enacted) bill text fetched from GovInfo (bytes decoded as UTF-8). H.R. 4346 became Public Law 117-167, signed Aug 9, 2022; it is popularly the 'CHIPS and Science Act of 2022.' The enrolled bill's formal long title is a Legislative Branch appropriations title because the CHIPS/Science text was substituted into the H.R. 4346 vehicle; Division A's own short title is 'CHIPS Act of 2022.' Sponsor of the underlying vehicle is not present in the enrolled XML, so sponsor is null (not fabricated). MECHANISMS (do NOT sum across them): (1) 'appropriation' = the CHIPS direct appropriations in Division A ('there is appropriated to the Fund ... out of amounts in the Treasury not otherwise appropriated') plus the two Division C Supreme Court-security supplementals ('The following sums are appropriated'). These are the only figures counted as spending; they total $54,219,400,000 = CHIPS for America Fund $50B (FY2022 $24B, of which $19B manufacturing incentives/$2B NSTC/$2.5B advanced packaging/$0.5B metrology; FY2023 $7B; FY2024 $6.3B; FY2025 $6.1B; FY2026 $6.6B) + Defense Fund $2B ($400M x5) + International Fund $0.5B ($100M x5) + Workforce & Education Fund $0.2B + Public Wireless Supply Chain Innovation (Open RAN) Fund $1.5B + Division C $19.4M. Multi-year funds are enumerated by fiscal-year figure so the total is non-overlapping and matches the widely-cited ~$54.2B. The FY2022 '$19B/$2B/$2.5B/$0.5B' carve-outs sum to that year's $24B top line; do NOT add them to a separate $24B line. (2) 'loan_guarantee_ceiling' = the $75,000,000,000 gross-obligation limit on direct loans/guarantees financed from the Fund (Sec.102(a)(2)(B)); this backstops lending and spends NO cash — excluded from the pie. Within the appropriated $19B (FY2022 sec.9902) the Act also carves up to $6B for loan/guarantee SUBSIDY COST and $2B for mature-node ('legacy chip') assistance; these are USES of the $19B, not separate appropriations, so they are not listed separately (would double-count). (3) 'authorization' = the entire 'Science' half (Division B): 'there are authorized to be appropriated $X' is a CEILING on FUTURE appropriations, i.e., permission, NOT money. The headline ~$170B+ 'CHIPS and Science' figure is dominated by these authorizations (NSF ramps $11.9B->$18.9B/yr, ~$81B/5yr; DOE Office of Science ~$8.9B->$10.8B/yr, ~$50B/5yr; NIST ~$1.55B->$2.28B/yr; EDA Regional Tech Hubs $10B; etc.). Authorization sub-allocations are NESTED (title total -> program -> named project) and MUST NOT be summed with their parents: e.g. NSF's TIP Directorate ($1.5B FY2023) sits inside NSF's R&RA/total; Basic Energy Sciences ($2.685B FY2023) sits inside DOE Office of Science; and the named national-lab construction items (Fermilab PIP-II ~$1.35B, Electron-Ion Collider ~$1.09B, Spallation Neutron Source proton power upgrade ~$1.19B) are cited at one representative fiscal year and sit inside the DOE physics program authorizations. Congress.gov roll-call and per-project earmark tables are separate documents, not this text. TAX CREDIT NOT INCLUDED: Sec.107 creates the 25% Advanced Manufacturing Investment Credit (new IRC sec.48D) — '25 percent of the qualified investment ... with respect to any advanced manufacturing facility'; it carries NO dollar figure in the operative text. Its cost (~$24B/10yr per JCT/CBO) lives only in the CBO cost estimate (publication 58319, hr4346_chip.pdf). It is intentionally OMITTED as a line item because CBO's server returned HTTP 403 to programmatic fetch, so the figure could not be string-verified against a keyless source per the 'omit if unverifiable' rule. spending_source is therefore 'bill_text' (all shipped dollars are verbatim from the enrolled text).